Portage Road project update for the week of June 10 to 14, 2024:

  • Continued installation of storm sewer pipe

  • Continued installation of sanitary sewer pipe

  • Installation of sanitary sewer manhole

  • Water sampling of temporary line prior to start-up


Work scheduled for this week:

  • Water shut-off planned for installation of 2 isolation valves and a hydrant

  • Transfer residents to temporary water line

  • Begin installation of potable water main

  • Continue installation of storm sewer line through West River Road intersection

  • Continue installation of sanitary sewer line through West River Rd intersection  