Projet Portage à Grand-Sault

Update for the week of August 26 to 30 on the Portage Road project:

  • Continued installation of sanitary sewer line on Portage Rd.

  • Continued installation of storm sewer pipe on Portage Rd.

  • Continued installation of water mains on Portage Rd.

  • Sub-base spreading at the intersection of West River Rd. and Portage Rd.

 

Work scheduled for this week:

  • Finalizing the installation of the sanitary sewer line, storm sewer line and drinking water line on Portage Rd.

  • Preparing to transfer residents to the new main lines

  • Paving and sidewalk work on the section between boul. Broadway and Chapel Street and on Portage Rd.

 

 
 
 

Commenti


Municipal Building

131 Pleasant Street,

Suite 200

Grand Falls, N.B.

Canada

E3Z 1G6

Our contact details

info@grandsault.ca

506.475.7777

506.475.7779

Business Hours

Monday - Friday, 8:30 a.m. - 4:30 p.m. AST (Atlantic Standard Time)

  • Facebook
  • Instagram
  • Twitter

© 2025 Grand Falls Regional Municipality. All rights reserved.

bottom of page