top of page

Update for the week of June 24 to 28, 2024

Projet Portage Grand-Sault

Update for the week of June 24 to 28 on the Portage Road project:

  • Continued installation of sanitary sewer line on ch. Portage

  • Continued installation of storm sewer line on ch. Portage

  • Continued installation of water mains on ch. West River

  • Installation of sanitary sewer manhole

  • Installation of temporary water line on 2nd project sector

 

Work scheduled for this week:

  • Continue installation of sanitary sewer line on ch. Portage

  • Continue installation of storm sewer line on ch. Portage

  • Continue installation of water mains on chemin Portage and chemin West River

  • Connect the two water mains at the Portage/West River intersection

 

Comments


bottom of page